Carelton Bridge
The project was delivered over a 12-month period and comprised a range of civil engineering and structural works, including the following key phases:
- Enabling works, including site clearance, relocation of existing services, and protection of existing Uisce Éireann watermain infrastructure.
- Ground investigation, including site investigations and analysis to inform the design and construction works.
- Substructure construction, incorporating piling and pile cap installation.
- Soil-reinforced panel construction, involving significant reinforced earthworks undertaken in collaboration with Banagher Precast and Terratec.
- Bridge superstructure installation, comprising the installation of Banagher Precast three-span precast bridge beams, together with associated precast parapets. The total installed beam span measured 76 metres.
- Bridge safety features, including the installation of OBEX bridge handrails and associated safety barriers.
- River diversion works, carried out in collaboration with Inland Fisheries.
The project also required close coordination and collaboration with the M28 design team to ensure the integration of both project designs, facilitate the resolution of interface requirements, and achieve key programme milestones.